SH 99 Construction Updates
The design of SH 99 Segment H includes a new intersection at FM 1485 and SH 99 frontage roads in New Caney. Over the next 2 -3 weeks, crews will be working to complete the intersection. While crews complete the configuration, motorists can expect to travel modified routes along FM 1485 between Scott Gardner Road and Redbud Drive.
The two critical time periods of construction will be the weekends of August 7 and August 14, as crews will be implementing a flagging operation 24 hours a day.
Below you will find the flagging operation schedule and a map of the newly configured area that is scheduled to be completed on Monday, August 17. Please note that this schedule is subject to change based on weather conditions or any unforeseen circumstances.
*Flagging Operation Schedule
- 8:00PM Friday, August 7 through 6:00AM Monday, August 10
- 8:00PM Friday, August 14 through 6:00 AM Monday, August 17
*During flagging operations, motorists in the area can expect minor delays. 4951