Work continues at Kingwood High School. Here are the latest progress photos of all the new flooring being installed. KHS is still on pace to accept students and staff back in on March 19.
Wood floors were installed in the gyms and dance room
Tile and carpet are complete in 2000 wing classrooms
Cabinets are being installed in 2000 wing classrooms
Lower cabinets and countertops are installed in the science wing
Flooring is 90 percent complete in CTE area
Cabinets are being installed in CTE area
Tile flooring is being installed in the main corridors of administration, fine arts and lower CTE hallway
The indoor practice putting green is installed
Painting continues in administration offices
IT data cabling and system restoration continues
Installation continues of drinking fountains and in restrooms
Restroom installation is complete in the 2000 wing
They've definitely come a long way. Great job, Humble ISD!